PERM applied Nov 17 2011

Audit Received Feb 19 2012

Audit Replied March 19 2012

Audit Reason(s)

1. Proof of recruitment process.

2. Proof that US workers who applied for the advertised opening were rejected for lawful reasons

3. Proof that opening was advertised through employee referral program

Still waiting for a decision....

Link to comment
  • 2 weeks later...

Here is my info:

PERM applied Nov 16 2011

Audit Received Feb 21 2012

Audit Replied March 22 2012

Audit Reason(s)

1. Proof of recruitment process.

2. Proof that US workers who applied for the advertised opening were rejected for lawful reasons

i noticed that October 2011 audit applications are being processed. Fingers crossed...:-(